在我的pgfgantt
图表中,任务 6 和任务 7 重叠并且与其他任务相比看起来很粗。
\documentclass[xcolor=table]{beamer}
\usepackage{pgfgantt}
\usetheme{Madrid}
\begin{document}
\begin{frame}{Work plan}{Tasks}
\frametitle{Gantt charts}
\begin{ganttchart}[
today=18,
today rule/.style= {blue, thick},
x unit=0.25cm,
y unit title=0.5cm,
y unit chart=0.35cm,
title label font=\tiny,
bar label font=\tiny,
group label font=\tiny\bfseries,
milestone label font=\tiny\itshape,
vgrid, hgrid]{1}{36}
\gantttitle{2017}{12}
\gantttitle{2018}{24} \\
\gantttitle{October}{4}
\gantttitle{November}{4}
\gantttitle{December}{4}
\gantttitle{January}{4}
\gantttitle{February}{4}
\gantttitle{March}{4}
\gantttitle{April}{4}
\gantttitle{May}{4}
\gantttitle{June}{4} \\
\ganttbar[bar/.append style={fill=blue!40}]{Task 1}{1}{36} \\
\ganttbar[bar/.append style={fill=blue!10}]{Task 2}{5}{6} \\
\ganttbar[bar/.append style={fill=blue!10}]{Task 3}{8}{10} \\
\ganttbar[bar/.append style={fill=blue!10}]{Task 4}{11}{13} \\
\ganttbar[bar/.append style={fill=blue!10}]{Task 5}{12}{18} \\
\ganttmilestone{Task 5.1}{18}\\
\ganttbar[bar/.append style={fill=blue!40}]{Task 6}{13}{24}
\ganttbar[bar/.append style={fill=blue!40}]{Task 6}{29}{29}
\ganttbar[bar/.append style={fill=blue!40}]{Task 6}{31}{32}\\
\ganttbar[bar/.append style={fill=blue!40}]{Task 7}{25}{28}
\ganttbar[bar/.append style={fill=blue!40}]{Task 7}{33}{36} \\
\ganttbar[bar/.append style={fill=blue!40}]{Task 8}{30}{30} \\
\ganttbar[bar/.append style={fill=blue!40}]{Task 9}{17}{32} \\
\ganttmilestone{Task 9.1}{32}\\
\ganttbar[bar/.append style={fill=blue!40}]{Task 10}{30}{35} \\
\ganttmilestone{Task 11}{35}
\ganttlink{elem1}{elem2}
\ganttlink{elem2}{elem3}
\ganttlink{elem4}{elem5}
\ganttlink{elem6}{elem9}
\ganttlink{elem9}{elem7}
\ganttlink{elem7}{elem11}
\ganttlink{elem11}{elem8}
\ganttlink{elem8}{elem10}
\ganttlink{elem12}{elem13}
\ganttlink{elem14}{elem15}
\end{ganttchart}
\end{frame}
\end{document}
你能给我一个解决方案吗?谢谢。
答案1
它看起来很粗,因为Task 6
在同一个地方打印了三次。但我认为你只需要打印一次,所以在任务的最后两部分中将标签留空。例如,\ganttbar[bar/.append style={fill=blue!40}]{}{29}{29}
而不是\ganttbar[bar/.append style={fill=blue!40}]{Task 6}{29}{29}
。
\ganttset
顺便说一下,您可以通过使用图表内部来简化一些代码。
\documentclass[xcolor=table]{beamer}
\usepackage{pgfgantt}
\usetheme{Madrid}
\begin{document}
\begin{frame}{Work plan}{Tasks}
\frametitle{Gantt charts}
\begin{ganttchart}[
today=18,
today rule/.style= {blue, thick},
x unit=0.25cm,
y unit title=0.5cm,
y unit chart=0.35cm,
title label font=\tiny,
bar label font=\tiny,
group label font=\tiny\bfseries,
milestone label font=\tiny\itshape,
bar/.append style={fill=blue!40},
vgrid, hgrid]{1}{36}
\gantttitle{2017}{12}
\gantttitle{2018}{24} \\
\gantttitle{October}{4}
\gantttitle{November}{4}
\gantttitle{December}{4}
\gantttitle{January}{4}
\gantttitle{February}{4}
\gantttitle{March}{4}
\gantttitle{April}{4}
\gantttitle{May}{4}
\gantttitle{June}{4} \\
\ganttbar{Task 1}{1}{36} \\
\ganttset{bar/.append style={fill=blue!10}}
\ganttbar{Task 2}{5}{6} \\
\ganttbar{Task 3}{8}{10} \\
\ganttbar{Task 4}{11}{13} \\
\ganttbar{Task 5}{12}{18} \\
\ganttmilestone{Task 5.1}{18}\\
\ganttset{bar/.append style={fill=blue!40}}
\ganttbar{Task 6}{13}{24}
\ganttbar{}{29}{29} % <-- empty label
\ganttbar{}{31}{32}\\ % <-- empty label
\ganttbar{Task 7}{25}{28}
\ganttbar{}{33}{36} \\ % <-- empty label
\ganttbar{Task 8}{30}{30} \\
\ganttbar{Task 9}{17}{32} \\
\ganttmilestone{Task 9.1}{32}\\
\ganttbar{Task 10}{30}{35} \\
\ganttmilestone{Task 11}{35}
\ganttlink{elem1}{elem2}
\ganttlink{elem2}{elem3}
\ganttlink{elem4}{elem5}
\ganttlink{elem6}{elem9}
\ganttlink{elem9}{elem7}
\ganttlink{elem7}{elem11}
\ganttlink{elem11}{elem8}
\ganttlink{elem8}{elem10}
\ganttlink{elem12}{elem13}
\ganttlink{elem14}{elem15}
\end{ganttchart}
\end{frame}
\end{document}